QUALITY ASSURANCE MANUAL

What is this manual for?

This manual explains The WS TEAM BD LTD’s apparel QA processes,and the standards that all our Suppliers will be tested to when producing apparel for us. It is intended for use by all our apparel Suppliers, to familiarise themselves with our expectations prior to tendering for work; and, subsequently, as a reference guide to help Suppliers through the manufacturing phase.

Apart from this Quality Manual,for different buyer WS TEAM BD LTD. can request suppliers to follow additional Guideline.

QA Process Flow Chart

Apart from this Quality Manual,for different buyer WS TEAM BD LTD. can request suppliers to follow additional Guideline.

Handover to Factory by WS-TEAM Merchandiser,Technical Clarification given by
WS-TEAM QA

Proto Sample Submission

Checked by WS-TEAM QA

Lab Dips & Print Strike Off Submission

Checked by WS-TEAM QA Approved BY WS-TEAM Merchandiser

Lab Test (If Required)

Pre Production Sample Submission

Checked by WS-TEAM QA

Trim Card Submission

Approved By WS-TEAM Merchandiser

Pre Production Meeting Along with Production Size Set Sample

Conduct By WS-TEAM QA along with Merchandiser

Inline Inspection

Conduct by WS-TEAM QA

Final Inspection

Conduct by WS_TEAM QA/Buyer /3rd Party

Shipment Release

Confirmed By WS-TEAM Merchandiser

QA Process Descriptions

Specification

The garment specification provided by The WS TEAM BD LTD. This document consists of a style sheet,size chart, sketch, and details of fabrics, accessories, stitching and construction

Proto Sample

This sample must match the specification for approval of fit and construction and must be accompanied by the necessary paperwork. The sample must be made in fabrics and accessories that are of the correct weight, type, stretch factor, handle and finish as required by the specification. It is not possible to assess the fit and construction of garments if the fabric and accessories are not correct or as intended for bulk. *The samples must be measured prior to submission and measurement noted on the Size Specification Form.WS-TEAM QA Personel must be checked the sample before despatching to Buyer. *Samples that are found to have major fit and construction discrepancies or are made using different fabric will not be audited by WS-TEAM QA. *Supplier must ensure that garments are carefully checked prior to submission and if discrepancies are found, the sample should be remade.

Lab Dips and Print Strike-offs

Lab dips are to be sent to the WS TEAM Merchandiser for approval. Print strike-offs are approved by the WS-TEAM Merchandiser for colour and design only. All quality aspects of print strike-offs must be approved by WS- TEAM QA.

Lab Test

Third party lab tests may required on fabrics/Accessories/Finished Apparel. Details of the test requirements can be send during the order confirmation.

Preproduction Sample

The purpose of this sample is to issue final approval before production. Any fit or construction amendments requested in the Proto Sample must have been made on this sample ready for approval.
*The samples must be measured prior to submission and measurement noted on the Size Specification Form. WS-TEAM QA Personnel must be checked the sample before despatching to Buyer.
*Pre-production samples must be made up in the actual bulk fabric, with the actual bulk accessories, labels, swing tags, barcode stickers, etc.
*If fabric/Garment testing has been requested the lab test report must accompany this sample. An email copy of the report is acceptable.

Trim Card

3set of Trim card need to be submit to WS-TEAM Merchandiser for Bulk Production Release.
*Trim card must contain all Fabric/accessories/Packing & packaging materials.

Pre Production Meeting

For Each Order after approval of PP sample and Trim card Supplier need to offer PP meeting before starting the Bulk,along with production size set.

Inline Inspection

During production stage Each order will be inspected by WS-TEAM BD LTD. QA minimum 3times.
1st Inline Inspection after completing 10% to 20% Goods
2nd Inline Inspection after completing 40% to 50% Goods
3rd Inline Inspection after completing 70% to 80% Goods (If Required WS-TEAM LTD have the right to inspect the goods more than 3times).

Final Inspection

All orders will be inspected by WS-TEAM LTD. QA to AQL 2.5/4.0 standard before they are dispatched. *3days before planned Final Inspection date should be informed to concern WS- TEAM LTD Merchandiser & QA. Defects are categorised as either Critical, Major, or Minor.A single Critical defect will fail the order. The number of acceptable Major and Minor Defects varies by sample size. An inspection should only commence when all of the following conditions are met: 1. An PP sample garment with all relevant attachments is available. 2. Order details are available 4. Fabric and accessories test reports have been submitted and approved (If Any) 5. 100% of the Goods is completed and available(must include allstyles,sizes and colours as specified on order). *Whenever a lot failsSupplier must 100% inspect to eliminate all classification of defects. The lot should either be repaired or in the event this is not possible, the good separated from the bad and the shortage quantity re-made.

Shipment Release

Supplier need to communicate with WS-TEAM Merchandiser after immediate pass the Final Inspection for Ex Factory confirmation and WS Team need to follow the same with ultimate Buyer for Shipment Released.

Document Required

  1. Style Sheet
  2. Purchase order
  3. Measurement Chart
  4. Fabric & Accessories Details Sheet
  5. Proto sample Checklist
  6. PP Sample Checklist
  7. PP Meeting Doc
  8. Trim Card
  9. Inline Inspection Report
  10. Final Inspection Report
  11. Packing List

Sample Required

  1. Proto Sample\
  2. SMS Sample with Orange WS Team Seal (If Any).
  3. PP Sample with Blue WS Team Seal.
  4. Shipping Sample With Red WS Team Seal.